The tree crews on Route 15 this spring and the White's Ferry announcement in July were real progress. Neither one changed how anyone in Raspberry Falls gets around this fall. Route 15 between Battlefield Parkway and Montresor Road is still two lanes. The ferry at the end of Whites Ferry Road is still closed. Both projects now wait on a step that has to happen in Loudoun County, and neither has a date when it ends.
Both also meet at the same place. The widening plan rebuilds the signal at Whites Ferry Road, and the ferry's missing piece sits at the far end of that same road.
What the Spring Tree Clearing Was For
In early March, Loudoun County announced tree clearing along Route 15 on both sides of the road from Battlefield Parkway to Whites Ferry Road. The work was set to start the week of March 9 and run until mid-April 2026. A March 23 notice added a daily partial lane closure, starting Wednesday, March 25, on the exit ramp from Route 15 to Route 15 Business/Leesburg so crews could clear trees there, and said work in the general vicinity would continue through April. The county said the clearing was groundwork for relocating utilities. It did not mark the start of the widening itself.
The county's procurement documents explain what comes next. Utility lines that run along the corridor will be moved to the east side of Route 15 starting in 2026. That work will continue alongside construction, with segments staggered so they don't conflict with the order of roadwork. So most of the activity drivers will see on this stretch over the next stretch of months will be utility work. Paving comes later. There's no county closure notice for October 2026 tied to the widening, and the spring notices covered only March and April.
The Only Contract Out for Bids Is for Inspectors
The widening only covers about 3.5 miles. It starts at Battlefield Parkway, where Route 15 now drops from four lanes to two, and ends at Montresor Road. It will widen the road to two lanes in each direction, paid for with local money and regional Northern Virginia Transportation Authority funds.
The project used to be planned as two segments that met at Whites Ferry Road. In a May 19, 2026 Board of Supervisors item, staff reported that the Battlefield Parkway to Whites Ferry Road segment had been combined with the Whites Ferry Road to Montresor Road segment. The combined project has an estimated value of $86 million, and staff said a project that size may draw more bidders. The same item flagged "maintenance of traffic" as a major part of the construction, given how much traffic Route 15 carries.
As of mid-October, here is where the project stands:
- Construction engineering and inspection. The county issued a request for proposals on September 15, 2026, with proposals due October 13. This contract pays the firm that oversees construction. It isn't the construction contract.
- The construction contract itself. The county expects to advertise it in March 2027. No road builder has been named.
- Duration. The inspection solicitation estimates about 54 months, counting final completion, administrative closeout, VDOT audit and street acceptance.
The county hasn't published a completion date. The 54 months is a contract duration, not a calendar date. Even counted from this month, it runs into 2031.
What Changes at the Intersections
The design work is the most settled part of the project, and it lays out what each familiar intersection will become. According to the county's inspection solicitation:
- North King Street becomes a signalized Continuous Green "T," so traffic heading north on the Route 15 Bypass can keep going without stopping.
- Whites Ferry Road gets an updated signalized intersection. The plan calls for a signal here, not a roundabout.
- Montresor Road becomes a two-lane hybrid roundabout, with Limestone School Road realigned to connect to it.
- Limestone Branch loses its existing culvert. The stream will be relocated and the crossing replaced with two parallel two-span steel plate girder bridges.
- A shared-use path runs along the west side of the corridor. It will be 16 feet wide from Tuscarora High School on North King Street to Whites Ferry Road, then 10 feet wide from Whites Ferry Road to Montresor Road.
The same document lists the constraints the builders will face. They include overhead and underground power and communication lines, karst and limestone geology, the existing floodplain, neighboring private properties, and tie-ins to local roads and driveways. Driveway tie-ins in particular mean the work will reach right up to individual property entrances along the corridor.
North of Montresor Road, four lanes are much further off. The county's proposed FY 2027 capital plan shows a Phase 1 widening from Montresor Road to the Lucketts Bypass with about $7.4 million in FY 2027. The larger amounts land in FY 2031 and FY 2032, for a six-year total of about $37 million. The sections from the Lucketts Bypass to St. Clair Lane and from St. Clair Lane to Lovettsville Road are on the budget's list for future development. They aren't in the active six-year capital plan.
The Ferry Now Has a Public Owner on the Maryland Bank
Follow Whites Ferry Road east to the river and the other project comes into view. Montgomery County's release dates White's Ferry to 1786. It began as Conrad's Ferry and linked Loudoun with Montgomery County, Maryland, by a 300-yard cable across the Potomac, as Loudoun Now recounted this summer. Service stopped on December 28, 2020. A later Loudoun County study tied the shutdown to a broken cable and a Circuit Court opinion over the Virginia landing. That ruling came on November 23, 2020, and found that Rockland Farm had no legally established ferry landing on its property. The county's statement at the time called the dispute private litigation and noted that the court did not order the ferry to stop running.
On July 24, 2026, Montgomery County announced it would buy the Maryland side from Potomac Crossing, LLC, owned by Chuck and Stacy Kuhn. The county is paying $1.5 million for about 2.5 acres of riverfront at 24801 White's Ferry Road in Dickerson, including the store, ferry ramp, boat launch and storage buildings. The Kuhns donated the ferry boats, business assets and equipment, valued at more than $7 million. If service comes back, Montgomery County plans to run it as a public service.
The same release says the purchase alone won't restart service. Landing rights at the end of White's Ferry Road in Loudoun still need to be restored, and Montgomery County has no authority to acquire them.
The Landing That Decides It Is in Loudoun
The Virginia landing sits in the Catoctin District. Supervisor Caleb Kershner told Loudoun Now that talks with Rockland Farms representatives were ongoing:
"We've been having discussions with them in terms of some sort of transfer to the county or purchase or some sort of resolution as recently as this month. So, we continue to work on it on a regular basis."
Kershner declined to share details. He told the outlet that eminent domain is not an option he's interested in pursuing right now, and that he was optimistic because talks were still going. The Loudoun Times-Mirror reported that he doubted a Board majority would support eminent domain, and that more meetings were planned. Montgomery County Executive Marc Elrich, speaking to reporters, called eminent domain a possibility but "the last consideration," with negotiation coming first.
WTOP's coverage gave no date for the ferry to reopen. No Loudoun Board vote, resolution or announced agreement on the landing has been made public since late July.
Why Whites Ferry Road Ties It Together
These two projects have different owners, different funding and different hurdles. For a household in Raspberry Falls, they show up on the same map. Heading south, the route to Leesburg runs through the stretch the county plans to widen, starting at the rebuilt Whites Ferry Road signal and running through the new Continuous Green "T" at North King Street. Heading east, a river crossing into Montgomery County depends on a negotiation over a landing at the end of that same road.
In both cases, the outside parties have done their part. Montgomery County owns the Maryland bank and the boats. Regional NVTA money is part of the road budget, and the design is detailed down to bridge girders and path widths. The remaining steps belong to Loudoun. For the road, that means advertising and awarding a construction contract. For the ferry, it means securing a landing.
There are three public milestones to watch over the coming months:
- The award of the construction engineering and inspection contract, once proposals are in after the October 13, 2026 deadline.
- Advertisement of the construction contract, which the county expects in March 2027.
- Any Board of Supervisors action or announced agreement on the Virginia landing for White's Ferry.
When you're weighing a move or planning a sale near Route 15, the construction timeline belongs in the conversation, especially if the property's driveway connects to the corridor. Suzanne Ager follows the widening and the ferry talks closely and can go through how each stage might affect a specific Raspberry Falls property. Book an appointment when you're ready to talk it through.